Completed

Houses of Parliament — New Fire Main

Method: Shaft & heading · Tie-in via bespoke fabricated steel section · Completed

illustrative — photography comingCullen Utilities craning in a large valve beside the Houses of Parliament
Situation

A new 225mm PE fire main was needed for the Houses of Parliament, running from Parliament Square to the southern entrance gates.

Challenge

Crossing one of London's busiest, most utility-congested roads on a security-sensitive site — then discovering the existing main was deeper than recorded and fouling live HV cables.

Solution

A shaft onto the existing 30-inch trunk main with a new tee for the cross connection; when the HV clash was found, a heading was driven to cut back and tie in a bespoke fabricated steel section.

Result

Completed. Replanned from four phases to two; the programme was cut from six weeks to four, running two gangs 24/7 on 12-hour shifts.

The brief

The Houses of Parliament needed a new 225mm PE fire main, running from Parliament Square to the southern entrance gates. The route crossed one of the busiest, most utility-congested roads in London, so the works had to be tightly phased around the sensitive traffic environment — originally planned as four phases to get the new main safely commissioned.

Why the plan changed mid-job

The team installed a shaft onto the existing 30-inch trunk main and fitted a new 30-inch × 200mm tee for the cross connection, laying the new main out to the centre of the second lane. Once backfilled and reinstated, traffic management was struck and reset for phase two — excavating on from the end of the new main through to the gates.

Pipe going in via lifting crane

‍

That's where the job stopped going to plan. Exposing the existing main at the gates, the team found it deeper than recorded — and clashing with live HV cables. Ground conditions nobody had on record. The fix meant driving a heading so the previously installed main could be cut back and tied in with a bespoke fabricated steel section, rather than the straightforward connection that had been designed for.

The method

To hold the compressed programme through the added complexity, the team worked round the clock — two gangs covering the job 24/7 on 12-hour shifts.

‍

Where it stands

Completed. What was planned as four phases was replanned down to two, and — running two gangs on 24/7, 12-hour shifts — the programme was cut from six weeks to four, despite the mid-job HV cable clash and one of the most congested utility corridors in London.

Have a job like one of these?

Send the situation and the constraints, and we'll tell you how we'd approach it.